Stay strong, N. 34th Street commuters. Your not-that-long, regional nightmare is almost over.

The final asphalt paving on N 34th street was completed this week, less than a month after the project began.  The Seattle Department of Transportation (SDOT) began in early July to repave N 34th Street from Fremont Avenue N to Stone Way N.

Work remaining includes installation of new lane markings and a new green bike box, in addition to a significant amount of sidewalk work. The project is scheduled to reach substantial completion in approximately two weeks.

For more information about the project, visit the project web site at:  http://www.seattle.gov/transportation/pave_n34th.htm.